Natural Gas Pipeline Notice 45867

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  6931794-NATURAL GAS PIPELINE CO. Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  03/06/2025 10:37:03AM Notice End Date/Time:  03/07/2025 9:00:00am
Post Date/Time:  3/6/2025 10:37:03 AM Notice ID: 45867
Reqrd Rsp:  1 Rsp Date:  03/06/2025
Notice Stat Desc:  SUPERSEDE Prior Notice:  45848
Subject:  SEG 8 - STA MAINTENANCE (CS 169) - UPD 1
Notice Text:

SEGMENT 8 – STATION MAINTENANCE – COMPRESSOR STATION 169 – UPDATE 1

 

The maintenance start date has been changed, as noted below.  See previous Notice ID 45848 dated February 27, 2025.

 

As posted on Natural's Outage Impact Report (X24-1331865), Natural will be performing station maintenance at Compressor Station 169 (CS 169), located in Deaf Smith County, Texas (Segment 8 of Natural's Permian Zone).  This maintenance work requires Natural to reduce its operating capacity, thus limiting Natural's throughput capacity northbound through CS 169.

 

The scheduling constraint will be at CS 167; therefore, any gas received south of CS 167 for delivery north of CS 167 will be impacted for the duration of this restriction.  For scheduling purposes, the Permian Pool (LOC 25077) is located south of the constraint.  Additionally, firm transportation nominated from receipt points south of CS 167 (including the Permian Pool) for injection at any storage point will be impacted.

 

As such, effective for gas day Tuesday, April 15, 2025 (previously Monday, April 14, 2025), Timely Cycle, and continuing through gas day Friday, April 18, 2025, Natural will schedule Primary Firm and Secondary in-path Firm transports to no less than 90% of contract MDQ through CS 167.  AOR/ITS and Secondary out-of-path Firm transports will not be available for the duration of this outage.

 

The stated scheduling percentage is based upon the current level of firm capacity contracted for during this restriction and is subject to change based upon operational conditions and Shipper utilization.

 

Continue to monitor Natural's interactive website for any updates during this outage.  Please contact your Account Director or Scheduling Representative if you have any questions.

TSP/TSP Name:  6931794-NATURAL GAS PIPELINE CO. Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  03/06/2025 10:37:03AM Notice End Date/Time:  03/07/2025 9:00:00am
Post Date/Time:  3/6/2025 10:37:03 AM Notice ID: 45867
Reqrd Rsp:  1 Rsp Date:  03/06/2025
Notice Stat Desc:  SUPERSEDE Prior Notice:  45848
Subject:  SEG 8 - STA MAINTENANCE (CS 169) - UPD 1
Notice Text:

SEGMENT 8 – STATION MAINTENANCE – COMPRESSOR STATION 169 – UPDATE 1

 

The maintenance start date has been changed, as noted below.  See previous Notice ID 45848 dated February 27, 2025.

 

As posted on Natural's Outage Impact Report (X24-1331865), Natural will be performing station maintenance at Compressor Station 169 (CS 169), located in Deaf Smith County, Texas (Segment 8 of Natural's Permian Zone).  This maintenance work requires Natural to reduce its operating capacity, thus limiting Natural's throughput capacity northbound through CS 169.

 

The scheduling constraint will be at CS 167; therefore, any gas received south of CS 167 for delivery north of CS 167 will be impacted for the duration of this restriction.  For scheduling purposes, the Permian Pool (LOC 25077) is located south of the constraint.  Additionally, firm transportation nominated from receipt points south of CS 167 (including the Permian Pool) for injection at any storage point will be impacted.

 

As such, effective for gas day Tuesday, April 15, 2025 (previously Monday, April 14, 2025), Timely Cycle, and continuing through gas day Friday, April 18, 2025, Natural will schedule Primary Firm and Secondary in-path Firm transports to no less than 90% of contract MDQ through CS 167.  AOR/ITS and Secondary out-of-path Firm transports will not be available for the duration of this outage.

 

The stated scheduling percentage is based upon the current level of firm capacity contracted for during this restriction and is subject to change based upon operational conditions and Shipper utilization.

 

Continue to monitor Natural's interactive website for any updates during this outage.  Please contact your Account Director or Scheduling Representative if you have any questions.