Nautilus Pipeline Company Critical Notices

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Type Posted Effective End Identifier Status Subject Response
Force Majeure 11/11/24 11/11/24 02/09/25 155108 Nautilus - Hurricane Rafael - Return to Ship Shoal 207A Platform
Force Majeure 11/11/24 11/11/24 02/09/25 155086 Nautilus - Hurricane Rafael - SS-207A Platform Loss of Power - Update
Force Majeure 11/10/24 11/10/24 02/08/25 155051 Nautilus - Hurricane Rafael - SS-207A Platform Loss of Power
Operational Flow Order 11/07/24 11/07/24 02/05/25 154952 Nautilus - Hurricane Rafael - Evacuation of all Personnel at SS-207A Platform
Pipeline Conditions 10/14/24 10/14/24 01/12/25 153884 Nautilus - Neptune Plant Capacity Constraint - Update
Capacity Constraint 10/10/24 10/11/24 10/12/24 153728 Nautilus Pipeline Conditions for 10/11/2024
Capacity Constraint 10/09/24 10/10/24 10/11/24 153704 Nautilus Pipeline Conditions for 10/10/2024
Capacity Constraint 10/09/24 10/09/24 10/10/24 153703 Nautilus Pipeline Conditions for 10/9/2024 - INTRADAY
Pipeline Conditions 10/09/24 10/09/24 01/07/25 153668 Nautilus - Neptune Plant Capacity Constraint