Southern Natural Gas Notice 710112

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  6900518-SOUTHERN NATURAL GAS CO. Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  12/02/2024 3:34:35PM Notice End Date/Time:  12/03/2024 9:00:00am
Post Date/Time:  12/2/2024 3:34:35 PM Notice ID: 710112
Reqrd Rsp:  1 Rsp Date:  12/02/2024
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  Update #1 Sched Maint Gwinville SEG 410
Notice Text:

Update to Scheduled Unit Maintenance – Gwinville Compressor Station (Segment 410 – Gwinville East) Update #1

The scheduled unit maintenance at the Gwinville compressor station scheduled for December 4th, 2024, through December 6th, 2024, has been re-scheduled to December 16th, 2024, through December 18th, 2024. As a result, Segment 410 (Gwinville East) capacity of 1,802 Mdth/d will be impacted by 155 Mdth/d, effective Timely cycle, gas day, Monday December 16th, 2024, through Wednesday December 18th, 2024.

Please continue to reference our weekly EBB postings. If you have any questions, please contact your Scheduling Representative or Account Manager.

 

SNG Gas Control

 

TSP/TSP Name:  6900518-SOUTHERN NATURAL GAS CO. Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  12/02/2024 3:34:35PM Notice End Date/Time:  12/03/2024 9:00:00am
Post Date/Time:  12/2/2024 3:34:35 PM Notice ID: 710112
Reqrd Rsp:  1 Rsp Date:  12/02/2024
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  Update #1 Sched Maint Gwinville SEG 410
Notice Text:

Update to Scheduled Unit Maintenance – Gwinville Compressor Station (Segment 410 – Gwinville East) Update #1

The scheduled unit maintenance at the Gwinville compressor station scheduled for December 4th, 2024, through December 6th, 2024, has been re-scheduled to December 16th, 2024, through December 18th, 2024. As a result, Segment 410 (Gwinville East) capacity of 1,802 Mdth/d will be impacted by 155 Mdth/d, effective Timely cycle, gas day, Monday December 16th, 2024, through Wednesday December 18th, 2024.

Please continue to reference our weekly EBB postings. If you have any questions, please contact your Scheduling Representative or Account Manager.

 

SNG Gas Control