Southern Natural Gas Notice 710474
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP/TSP Name: 6900518-SOUTHERN NATURAL GAS CO. | Critical: Y |
Notice Type Desc (1): PIPELINE CONDITIONS | Notice Type Desc (2): CURRENT PIPELINE CONDITIONS |
Notice Eff Date/Time: 03/02/2025 1:59:24PM | Notice End Date/Time: 03/03/2025 9:00:00am |
Post Date/Time: 3/2/2025 1:59:24 PM | Notice ID: 710474 |
Reqrd Rsp: 1 | Rsp Date: 03/02/2025 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: Pipeline Conditions as of 03-03-2025 |
Effective Timely Cycle for gas day Monday, March 03, 2025, and continuing until further notice, SNG restricted the following:
OPERATIONAL FLOW ORDERS (OFO)
NONE
RESTRICTIONS (POINT)
· 605400 (BBTBAMA/SNG DUNCANVILLE) – Exceeds Operating Capacity – Reductions into PIP services
RESTRICTIONS (SEGMENT)
· 380 (SNG-SESH) - Exceeds Operating Capacity – Reductions into OP Services
· 400 (PICKENS TO GWINVILLE) - Exceeds Operating Capacity – Reductions through OP Services
RESTRICTIONS (LINEPACK)
NONE
RESTRICTIONS (STORAGE)
NONE
Type 3 / 4 OFO Probability (Unlikely (UL); Likely (L); Too Close to Call (TC); Highly Likely (HL)
March 3, 2025 – UL
Type 6 OFO Probability (Unlikely (UL); Too Close to Call (TC); Highly Likely (HL)
March 3, 2025 – UL for Short and UL for Long Imbalances
TSP/TSP Name: 6900518-SOUTHERN NATURAL GAS CO. | Critical: Y |
Notice Type Desc (1): PIPELINE CONDITIONS | Notice Type Desc (2): CURRENT PIPELINE CONDITIONS |
Notice Eff Date/Time: 03/02/2025 1:59:24PM | Notice End Date/Time: 03/03/2025 9:00:00am |
Post Date/Time: 3/2/2025 1:59:24 PM | Notice ID: 710474 |
Reqrd Rsp: 1 | Rsp Date: 03/02/2025 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: Pipeline Conditions as of 03-03-2025 |
Effective Timely Cycle for gas day Monday, March 03, 2025, and continuing until further notice, SNG restricted the following:
OPERATIONAL FLOW ORDERS (OFO)
NONE
RESTRICTIONS (POINT)
· 605400 (BBTBAMA/SNG DUNCANVILLE) – Exceeds Operating Capacity – Reductions into PIP services
RESTRICTIONS (SEGMENT)
· 380 (SNG-SESH) - Exceeds Operating Capacity – Reductions into OP Services
· 400 (PICKENS TO GWINVILLE) - Exceeds Operating Capacity – Reductions through OP Services
RESTRICTIONS (LINEPACK)
NONE
RESTRICTIONS (STORAGE)
NONE
Type 3 / 4 OFO Probability (Unlikely (UL); Likely (L); Too Close to Call (TC); Highly Likely (HL)
March 3, 2025 – UL
Type 6 OFO Probability (Unlikely (UL); Too Close to Call (TC); Highly Likely (HL)
March 3, 2025 – UL for Short and UL for Long Imbalances