Southern Natural Gas Notice 710482
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP/TSP Name: 6900518-SOUTHERN NATURAL GAS CO. | Critical: Y |
Notice Type Desc (1): MAINTENANCE | Notice Type Desc (2): MAINTENANCE |
Notice Eff Date/Time: 03/04/2025 2:23:42PM | Notice End Date/Time: 03/05/2025 9:00:00am |
Post Date/Time: 3/4/2025 2:23:42 PM | Notice ID: 710482 |
Reqrd Rsp: 1 | Rsp Date: 03/04/2025 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: Update # 1 Sched Maint Thomaston Seg 530 |
Update to Scheduled Pipeline Maintenance – South Main Loop Line (Segment 530 – Thomaston East) Update #1
The scheduled pipeline maintenance on the South Main loop line east of Thomaston (Segment 530 – Thomaston East) located in Crawford County, GA scheduled for March 11th, 2025, to March 14th, 2025, has been re-scheduled for March 7th, 2025, to March 10th, 2025. As a result, Segment 530 (Thomaston East) capacity of 900 Mdth/d will be impacted by 40 Mdth/d effective Timely Cycle, gas day, Friday, March 7th, 2025, through Monday, March 10th, 2025.
Please continue to reference our weekly EBB postings. If you have any questions, please contact your Scheduling Representative or Account Manager.
SNG Gas Control
TSP/TSP Name: 6900518-SOUTHERN NATURAL GAS CO. | Critical: Y |
Notice Type Desc (1): MAINTENANCE | Notice Type Desc (2): MAINTENANCE |
Notice Eff Date/Time: 03/04/2025 2:23:42PM | Notice End Date/Time: 03/05/2025 9:00:00am |
Post Date/Time: 3/4/2025 2:23:42 PM | Notice ID: 710482 |
Reqrd Rsp: 1 | Rsp Date: 03/04/2025 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: Update # 1 Sched Maint Thomaston Seg 530 |
Update to Scheduled Pipeline Maintenance – South Main Loop Line (Segment 530 – Thomaston East) Update #1
The scheduled pipeline maintenance on the South Main loop line east of Thomaston (Segment 530 – Thomaston East) located in Crawford County, GA scheduled for March 11th, 2025, to March 14th, 2025, has been re-scheduled for March 7th, 2025, to March 10th, 2025. As a result, Segment 530 (Thomaston East) capacity of 900 Mdth/d will be impacted by 40 Mdth/d effective Timely Cycle, gas day, Friday, March 7th, 2025, through Monday, March 10th, 2025.
Please continue to reference our weekly EBB postings. If you have any questions, please contact your Scheduling Representative or Account Manager.
SNG Gas Control