Southern Natural Gas Notice 710522

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  6900518-SOUTHERN NATURAL GAS CO. Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  03/13/2025 4:43:08PM Notice End Date/Time:  03/14/2025 9:00:00am
Post Date/Time:  3/13/2025 4:43:08 PM Notice ID: 710522
Reqrd Rsp:  1 Rsp Date:  03/13/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  Outage Impact Report
Notice Text:

 

 

 

 

 

 

 

-Restrictions to Primary In-Path transportation services may be necessary.

 

 

 

SNG - Outage Impact Report

 

 

 

-Restrictions to In-Path transportation services may be necessary.

 

 

Seven Day Forecast (updated 03/13/25)

 

 

 

-Restrictions to Interruptible and Out of Path transportation services may be necessary.

 

 

 

 

 

 

-No anticipated impact to transportation services.

 

 

Station / Seg

 

Est Nominal Design Capacity (Thousand Dth)

 

Monday (3/17)

 

Tuesday (3/18)

 

Wednesday (3/19)

 

Thursday (3/20)

 

Friday (3/21)

 

Saturday (3/22)

 

Sunday (3/23)

 

 

Primary Outage(s) that may Impact Throughput

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Onward (segment 30)

 

 

209

 

 

209

 

 

209

 

 

209

 

 

209

 

 

209

 

 

209

 

 

209

 

 

Duncanville Lateral (segment 90)

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

Dearmanville (segment 150)

 

 

355

 

 

355

 

 

355

 

 

355

 

 

355

 

 

355

 

 

355

 

 

355

 

 

White Castle (segment 340)

 

 

798

 

 

798

 

 

798

 

 

798

 

 

798

 

 

798

 

 

798

 

 

798

 

 

LA West Leg (segment 350)

 

 

798

 

 

798

 

733

(65)

 

733

(65)

 

733

(65)

 

733

(65)

 

733

(65)

 

733

(65)

Franklinton Compressor Station: Scheduled Unit Maintenance Proj-512216 (3/18/2025 - 3/31/2025)

 

Sesh (segment 380)

 

 

506

 

 

506

 

 

506

 

 

506

 

 

506

 

 

506

 

 

506

 

 

506

 

 

Gwinville Pool (segment 390)

 

 

1,707

 

1487

(220)

 

1487

(220)

 

1487

(220)

 

1487

(220)

 

 

1,707

 

 

1,707

 

 

1,707

Gwinville Compressor Station: Scheduled Station Maintenance Proj-5211P3 (3/3/2025 - 3/20/2025)

 

Gwinville (segment 400)

 

 

234

 

182

(52)

 

182

(52)

 

182

(52)

 

182

(52)

 

182

(52)

 

182

(52)

 

182

(52)

Gwinville Pickens Line north of Gwinville: Pipeline Maintenance(remediation) Proj-SNG-19050/20646 (3/17/2025 - 3/24/2025)

Gwinville Pickens Line south of Rankin: Pipeline Maintenance(remediation) Proj-SNG-19050 (3/17/2025 - 3/19/2025)

 

Enterprise (segment 430)

 

 

2,450

 

 

2,450

 

 

2,450

 

 

2,450

 

 

2,450

 

 

2,450

 

 

2,450

 

 

2,450

 

 

Ellerslie (segment 490)

 

 

1,663

 

 

1,663

 

 

1,663

 

 

1,663

 

 

1,663

 

 

1,663

 

 

1,663

 

 

1,663

 

 

Thomaston West (segment 490)

 

 

1,650

 

1605

(45)

 

1605

(45)

 

1605

(45)

 

1605

(45)

 

1605

(45)

 

1605

(45)

 

1605

(45)

Thomaston Compressor Station: Unscheduled Unit Outage Proj-52723 (1/30/2025 - 3/23/2025)

 

South Atlanta (segment 510)

 

 

537

 

 

537

 

 

537

 

 

537

 

 

537

 

 

537

 

 

537

 

 

537

 

 

Thomaston East (segment 530)

 

 

900

 

 

900

 

 

900

 

 

900

 

 

900

 

 

900

 

 

900

 

 

900

 

 

East/South Wrens (segment 560)

 

 

724

 

 

724

 

669

(55)

 

669

(55)

 

669

(55)

 

669

(55)

 

669

(55)

 

669

(55)

Wrens Compressor Station: Scheduled Unit Maintenance Proj-52885 (3/18/2025 - 3/31/2025)

 

South Georgia (segment 650)

 

 

143

 

 

143

 

 

143

 

 

143

 

 

143

 

 

143

 

 

143

 

 

143

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report. The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

 

 

 

-Restrictions to Primary In-Path transportation services may be necessary.

 

 

SNG - Outage Impact Report

 

 

-Restrictions to In-Path transportation services may be necessary.

 

March 2025 (updated 03/13/25)

 

-Restrictions to Interruptible and Out of Path transportation services may be necessary.

-No anticipated impact to transportation services.

 

Station / Seg

 

Est Nominal Design Capacity (Thousand Dth)

Week 1 (3/3 - 3/9)

Week 2 (3/10 - 3/16)

Week 3 (3/17 - 3/23)

Week 4 (3/24 - 3/30)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Onward (segment 30)

 

 

209

 

 

 

 

 

209

 

 

Duncanville Lateral (segment 90)

 

 

36

 

 

 

 

 

36

 

 

Dearmanville (segment 150)

 

 

355

 

 

 

 

 

355

 

 

White Castle (segment 340)

 

 

798

 

 

 

 

 

798

 

 

LA West Leg (segment 350)

 

 

798

 

 

 

 

733

(65)

Franklinton Compressor Station: Scheduled Unit Maintenance, Proj-512216 (3/18/2025 - 3/31/2025)

 

Sesh (segment 380)

 

 

506

 

 

 

 

 

506

 

 

 

Gwinville (segment 400)

 

 

234

 

 

 

 

 

65

(169)

Gwinville Pickens Line north of Gwinville: Pipeline Maintenance(remediation), Proj-SNG-19050/20646 (3/17/2025 - 3/24/2025)

Gwinville Pickens Line north of Gwinville: Pipeline Maintenance(remediation), Proj-SNG- 19050/20646/21938 (3/25/2025 - 4/4/2025)

Pickens Compressor Station: Scheduled Station Maintenance , Proj-4125 (3/25/2025 - 3/26/2025)

 

Enterprise (segment 430)

 

 

2,450

 

 

 

 

2200

(250)

Enterprise Compressor Station: Scheduled Unit Maintenance, Proj-522216 (3/24/2025 - 3/31/2025)

 

Ellerslie (segment 490)

 

 

1,663

 

 

 

 

 

1,663

 

 

South Atlanta (segment 510)

 

 

537

 

 

 

 

 

537

 

 

Thomaston East (segment 530)

 

 

900

 

 

 

 

 

900

 

 

East/South Wrens (segment 560)

 

 

724

 

 

 

 

669

(55)

Wrens Compressor Station: Scheduled Unit Maintenance, Proj-52885 (3/18/2025 - 3/31/2025)

 

South Georgia (segment 650)

 

 

143

 

 

 

 

 

143

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

 

-Restrictions to Primary In-Path transportation services may be necessary.

 

SNG - Outage Impact Report

 

 

-Restrictions to In-Path transportation services may be necessary.

 

April 2025 (updated 03/13/25)

 

 

-Restrictions to Interruptible and Out of Path transportation services may be necessary.

-No anticipated impact to transportation services.

 

Station / Seg

 

Est Nominal Design Capacity (Thousand Dth)

Week 1 (3/31 - 4/6)

Week 2 (4/7 - 4/13)

Week 3 (4/14 - 4/20)

Week 4 (4/21 - 4/27)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

 

Onward (segment 30)

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

 

Louisville East (segment 50)

 

 

520

 

 

520

 

210

(310)

 

210

(310)

 

275

(245)

2nd North Main Line east of Pickens: Pipeline Maintenance(remediation), Proj-SNG-19047 (4/21/2025 - 5/2/2025)

2nd North Main Line east of Pickens: Pipeline Maintenance(remediation), Proj-SNG-19047 (M) (4/8/2025 - 4/18/2025)

 

Duncanville Lateral (segment 90)

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

 

Pell City Station (segment 140)

 

 

474

 

 

474

 

 

474

 

 

474

 

304

(170)

Talladega Branch loop to Sylacauga line: Scheduled Pipeline Maintenance, Proj-SNG-36904 (M) (4/22/2025 - 4/24/2025)

 

 

Dearmanville (segment 150)

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

 

White Castle (segment 340)

 

 

772

 

 

772

 

 

772

 

 

772

 

 

772

 

 

 

LA West Leg (segment 350)

 

 

695

 

630

(65)

 

 

695

 

 

695

 

 

695

Franklinton Compressor Station: Scheduled Unit Maintenance, Proj-512216 (3/18/2025 - 3/31/2025)

 

 

Sesh (segment 380)

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

 

Gwinville Pool (segment 390)

 

 

1,607

 

1217

(390)

 

1217

(390)

 

1342

(265)

 

1342

(265)

Gwinville Compressor Station: Scheduled Station Maintenance, Proj-5211P4B (4/5/2025 - 4/12/2025) Gwinville Compressor Station: Scheduled Station Maintenance, Proj-5211P4C (4/12/2025 - 4/21/2025)

 

 

Gwinville (segment 400)

 

 

234

 

 

199

(35)

 

 

150

(84)

 

 

150

(84)

 

 

149

(85)

2nd North Main Line east of Pickens: Pipeline Maintenance(remediation), Proj-SNG-19047 (4/8/2025 - 4/18/2025)

Gwinville Pickens Line north of Gwinville: Pipeline Maintenance(remediation), Proj-SNG- 19050/20646/21938 (3/25/2025 - 4/4/2025)

Pickens Compressor Station: Scheduled Unit Maintenance , Proj-41251 (4/21/2025 - 5/11/2025)

 

 

Bay Springs (segment 420)

 

 

1,675

 

 

1,675

 

1485

(190)

 

 

1,675

 

 

1,675

Bay Springs Compressor Station: Scheduled Unit Maintenance, Proj-52163 (4/7/2025 - 4/10/2025)

 

 

Enterprise (segment 430)

 

 

2,306

 

2056

(250)

 

2136

(170)

 

 

2,306

 

 

2,306

Enterprise Compressor Station: Scheduled Unit Maintenance, Proj-522216 (3/24/2025 - 3/31/2025) Enterprise Compressor Station: Scheduled Unit Maintenance, Proj-522216 (4/1/2025 - 4/7/2025)

 

 

York (segment 440)

 

 

2,305

 

2125

(180)

 

2080

(225)

 

2125

(180)

 

2125

(180)

York Compressor Station: Scheduled Unit Maintenance, Proj-52301 (4/1/2025 - 10/31/2025) York Compressor Station: Scheduled Unit Maintenance, Proj-52303 (4/7/2025 - 4/9/2025)

 

 

Gallion (Segment 440)

 

 

2,300

 

2030

(270)

 

 

2,300

 

 

2,300

 

 

2,300

Gallion Compressor Station: Scheduled Unit Maintenance , Proj-523610 (3/31/2025 - 4/2/2025)

 

 

Selma (segment 460)

 

 

2,293

 

2043

(250)

 

 

2,293

 

 

2,293

 

 

2,293

Selma Compressor Station: Scheduled Unit Maintenance, Proj-52453 (4/2/2025 - 4/4/2025)

 

 

Auburn (segment 460)

 

 

1,953

 

 

1,953

 

 

1628

(325)

 

 

1628

(325)

 

 

1628

(325)

Auburn Compressor Station: Scheduled Unit Maintenance, Proj-52593 (4/23/2025 - 4/25/2025) South Main Loop Line east of Auburn: Scheduled Pipeline Maintenance, Proj-SNG-24941 (4/9/2025 - 4/23/2025)

South Main Loop Line west of Ellerslie: Scheduled Pipeline Maintenance, Proj-SNG-24942 (4/9/2025 - 4/23/2025)

 

 

Ellerslie (segment 490)

 

 

1,547

 

 

1,547

 

 

1,547

 

1317

(230)

 

 

1,547

Thomaston Compressor Station: Scheduled Unit Maintenance, Proj-52721 (4/14/2025 - 4/18/2025)

 

 

South Atlanta (segment 510)

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

 

Thomaston East (segment 530)

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

 

Hall Gate (segment 560)

 

 

705

 

635

(70)

 

635

(70)

 

635

(70)

 

635

(70)

Hall Gate Compressor Station: Scheduled Unit Maintenance, Proj-52833 (4/1/2025 - 5/11/2025)

 

East/South Wrens (segment 560)

 

 

680

 

625

(55)

 

 

680

 

 

680

 

 

680

Wrens Compressor Station: Scheduled Unit Maintenance, Proj-52885 (3/18/2025 - 3/31/2025)

 

 

South Georgia (segment 650)

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

 

 

Holy Trinity (segment 655)

 

 

127

 

 

127

 

97

(30)

 

97

(30)

 

 

127

Holy Trinity Compressor Station: Scheduled Station Maintenance (4/7/2025 - 4/12/2025) Holy Trinity Compressor Station: Scheduled Unit Maintenance, Proj-58051 (4/7/2025 - 4/12/2025)

Mainline #1 north of Holy Trinity Compressor Station: Scheduled Pipeline Maintenance (4/14/2025 - 4/20/2025)

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses. Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

 

 

-Restrictions to Primary In-Path transportation services may be necessary.

 

 

SNG - Outage Impact Report

 

 

-Restrictions to In-Path transportation services may be necessary.

 

 

May 2025 (updated 03/13/25)

 

 

-Restrictions to Interruptible and Out of Path transportation services may be necessary.

 

 

 

 

 

-No anticipated impact to transportation services.

 

Station / Seg

 

Est Nominal Design Capacity (Thousand Dth)

Week 1 (4/28 - 5/4)

Week 2 (5/5 - 5/11)

Week 3 (5/12 - 5/18)

Week 4 (5/19 - 5/25)

Week 5 (5/26 - 6/1)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Onward (segment 30)

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

Louisville East (segment 50)

 

 

520

 

275

(245)

 

 

520

 

 

520

 

 

520

 

 

520

2nd North Main Line east of Pickens: Pipeline Maintenance(remediation), Proj-SNG-19047 (4/21/2025 - 5/2/2025)

 

Duncanville Lateral (segment 90)

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

Dearmanville (segment 150)

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

White Castle (segment 340)

 

 

772

 

 

772

 

 

772

 

 

772

 

 

772

 

 

772

 

 

LA West Leg (segment 350)

 

 

695

 

 

695

 

 

695

 

 

695

 

535

(160)

 

535

(160)

Duck Lake Franklinton Line north of White Castle: Scheduled Pipeline Maintenance, Proj-SNG-22856 (5/22/2025 - 6/5/2025)

Duck Lake Franklinton Line north of White Castle: Scheduled Pipeline Maintenance, Proj-SNG-2753 (5/22/2025 - 6/5/2025)

 

Sesh (segment 380)

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

Gwinville Pool (segment 390)

 

 

1,607

 

1217

(390)

 

1217

(390)

 

 

1,607

 

 

1,607

 

 

1,607

Gwinville Compressor Station: Scheduled Station Maintenance, Proj-521113P5A (4/29/2025 - 5/2/2025)

Gwinville Compressor Station: Scheduled Station Maintenance, Proj-5211P5 (4/28/2025 - 5/8/2025)

 

 

Gwinville (segment 400)

 

 

234

 

 

0

(234)

 

 

149

(85)

 

 

150

(84)

 

 

150

(84)

 

 

234

2nd North Main Line east of Pickens: Pipeline Maintenance(remediation), Proj-SNG-19047 (5/5/2025 - 5/21/2025)

Pickens Compressor Station: Scheduled Unit Maintenance , Proj-41251 (4/21/2025 - 5/11/2025) 5/2/2025)

Gwinville Compressor Station: Scheduled Station Maintenance, Proj-5211P5 (4/28/2025 - 5/8/2025)

 

Enterprise (segment 430)

 

 

2,306

 

 

2,306

 

 

2,306

 

 

2,306

 

 

2,306

 

 

2,306

 

 

York (segment 440)

 

 

2,305

 

2125

(180)

 

2125

(180)

 

2125

(180)

 

2125

(180)

 

2125

(180)

York Compressor Station: Scheduled Unit Maintenance, Proj-52301 (4/1/2025 - 10/31/2025)

 

Selma (segment 460)

 

 

2,293

 

 

2,293

 

 

2,293

 

1993

(300)

 

 

2,293

 

 

2,293

South Main Loop Line east of Selma: Scheduled Pipeline Maintenance, Proj-SNG-24945 (5/12/2025 - 5/18/2025)

 

Auburn (segment 460)

 

 

1,953

 

1813

(140)

 

1813

(140)

 

 

1,953

 

 

1,953

 

 

1,953

South Main Loop Line west of Ellerslie: Scheduled Pipeline Maintenance, Proj-SNG-24943 (4/28/2025 - 5/11/2025)

South Main Loop Line west of Ellerslie: Scheduled Pipeline Maintenance, Proj-SNG-24944 (4/28/2025 - 5/11/2025)

 

Ellerslie (segment 490)

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

South Atlanta (segment 510)

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

Thomaston East

(segment 530)

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

Hall Gate (segment 560)

 

 

705

 

635

(70)

 

635

(70)

 

 

705

 

 

705

 

 

705

Hall Gate Compressor Station: Scheduled Unit Maintenance, Proj-52833 (4/1/2025 - 5/11/2025)

 

South Georgia (segment 650)

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses. Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

 

 

-Restrictions to Primary In-Path transportation services may be necessary.

 

 

SNG - Outage Impact Report

 

 

-Restrictions to In-Path transportation services may be necessary.

 

June 2025 (updated 03/13/25)

 

-Restrictions to Interruptible and Out of Path transportation services may be necessary.

-No anticipated impact to transportation services.

 

Station / Seg

 

Est Nominal Design Capacity (Thousand Dth)

Week 1 (6/2 - 6/8)

Week 2 (6/9 - 6/15)

Week 3 (6/16 - 6/22)

Week 4 (6/23 - 6/29)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Onward (segment 30)

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

Duncanville Lateral (segment 90)

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

Dearmanville (segment 150)

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

White Castle (segment 340)

 

 

772

 

 

772

 

 

772

 

 

772

 

 

772

 

 

 

LA West Leg (segment 350)

 

 

695

 

 

535

(160)

 

 

595

(100)

 

 

595

(100)

 

 

695

Duck Lake Franklinton Line north of White Castle: Scheduled Pipeline Maintenance, Proj-SNG-22856 (5/22/2025 - 6/5/2025)

Duck Lake Franklinton Line north of White Castle: Scheduled Pipeline Maintenance, Proj-SNG-2753 (5/22/2025 - 6/5/2025)

White Castle Franklinton Loop Line north of White Castle: Scheduled Pipeline Maintenance Proj-SNG-22856 (6/06/2025 - 6/17/2025)

 

Sesh (segment 380)

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

Gwinville (segment 400)

 

 

234

 

 

234

 

 

234

 

 

234

 

 

234

 

 

Enterprise (segment 430)

 

 

2,306

 

 

2,306

 

 

2,306

 

 

2,306

 

 

2,306

 

 

York (segment 440)

 

 

2,305

 

2125

(180)

 

2125

(180)

 

2125

(180)

 

2125

(180)

York Compressor Station: Scheduled Unit Maintenance, Proj-52301 (4/1/2025 - 10/31/2025)

 

Ellerslie (segment 490)

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

South Atlanta (segment 510)

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

Thomaston East (segment 530)

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

South Georgia (segment 650)

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.

 

TSP/TSP Name:  6900518-SOUTHERN NATURAL GAS CO. Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  03/13/2025 4:43:08PM Notice End Date/Time:  03/14/2025 9:00:00am
Post Date/Time:  3/13/2025 4:43:08 PM Notice ID: 710522
Reqrd Rsp:  1 Rsp Date:  03/13/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  Outage Impact Report
Notice Text:

 

 

 

 

 

 

 

-Restrictions to Primary In-Path transportation services may be necessary.

 

 

 

SNG - Outage Impact Report

 

 

 

-Restrictions to In-Path transportation services may be necessary.

 

 

Seven Day Forecast (updated 03/13/25)

 

 

 

-Restrictions to Interruptible and Out of Path transportation services may be necessary.

 

 

 

 

 

 

-No anticipated impact to transportation services.

 

 

Station / Seg

 

Est Nominal Design Capacity (Thousand Dth)

 

Monday (3/17)

 

Tuesday (3/18)

 

Wednesday (3/19)

 

Thursday (3/20)

 

Friday (3/21)

 

Saturday (3/22)

 

Sunday (3/23)

 

 

Primary Outage(s) that may Impact Throughput

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Onward (segment 30)

 

 

209

 

 

209

 

 

209

 

 

209

 

 

209

 

 

209

 

 

209

 

 

209

 

 

Duncanville Lateral (segment 90)

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

Dearmanville (segment 150)

 

 

355

 

 

355

 

 

355

 

 

355

 

 

355

 

 

355

 

 

355

 

 

355

 

 

White Castle (segment 340)

 

 

798

 

 

798

 

 

798

 

 

798

 

 

798

 

 

798

 

 

798

 

 

798

 

 

LA West Leg (segment 350)

 

 

798

 

 

798

 

733

(65)

 

733

(65)

 

733

(65)

 

733

(65)

 

733

(65)

 

733

(65)

Franklinton Compressor Station: Scheduled Unit Maintenance Proj-512216 (3/18/2025 - 3/31/2025)

 

Sesh (segment 380)

 

 

506

 

 

506

 

 

506

 

 

506

 

 

506

 

 

506

 

 

506

 

 

506

 

 

Gwinville Pool (segment 390)

 

 

1,707

 

1487

(220)

 

1487

(220)

 

1487

(220)

 

1487

(220)

 

 

1,707

 

 

1,707

 

 

1,707

Gwinville Compressor Station: Scheduled Station Maintenance Proj-5211P3 (3/3/2025 - 3/20/2025)

 

Gwinville (segment 400)

 

 

234

 

182

(52)

 

182

(52)

 

182

(52)

 

182

(52)

 

182

(52)

 

182

(52)

 

182

(52)

Gwinville Pickens Line north of Gwinville: Pipeline Maintenance(remediation) Proj-SNG-19050/20646 (3/17/2025 - 3/24/2025)

Gwinville Pickens Line south of Rankin: Pipeline Maintenance(remediation) Proj-SNG-19050 (3/17/2025 - 3/19/2025)

 

Enterprise (segment 430)

 

 

2,450

 

 

2,450

 

 

2,450

 

 

2,450

 

 

2,450

 

 

2,450

 

 

2,450

 

 

2,450

 

 

Ellerslie (segment 490)

 

 

1,663

 

 

1,663

 

 

1,663

 

 

1,663

 

 

1,663

 

 

1,663

 

 

1,663

 

 

1,663

 

 

Thomaston West (segment 490)

 

 

1,650

 

1605

(45)

 

1605

(45)

 

1605

(45)

 

1605

(45)

 

1605

(45)

 

1605

(45)

 

1605

(45)

Thomaston Compressor Station: Unscheduled Unit Outage Proj-52723 (1/30/2025 - 3/23/2025)

 

South Atlanta (segment 510)

 

 

537

 

 

537

 

 

537

 

 

537

 

 

537

 

 

537

 

 

537

 

 

537

 

 

Thomaston East (segment 530)

 

 

900

 

 

900

 

 

900

 

 

900

 

 

900

 

 

900

 

 

900

 

 

900

 

 

East/South Wrens (segment 560)

 

 

724

 

 

724

 

669

(55)

 

669

(55)

 

669

(55)

 

669

(55)

 

669

(55)

 

669

(55)

Wrens Compressor Station: Scheduled Unit Maintenance Proj-52885 (3/18/2025 - 3/31/2025)

 

South Georgia (segment 650)

 

 

143

 

 

143

 

 

143

 

 

143

 

 

143

 

 

143

 

 

143

 

 

143

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report. The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

 

 

 

-Restrictions to Primary In-Path transportation services may be necessary.

 

 

SNG - Outage Impact Report

 

 

-Restrictions to In-Path transportation services may be necessary.

 

March 2025 (updated 03/13/25)

 

-Restrictions to Interruptible and Out of Path transportation services may be necessary.

-No anticipated impact to transportation services.

 

Station / Seg

 

Est Nominal Design Capacity (Thousand Dth)

Week 1 (3/3 - 3/9)

Week 2 (3/10 - 3/16)

Week 3 (3/17 - 3/23)

Week 4 (3/24 - 3/30)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Onward (segment 30)

 

 

209

 

 

 

 

 

209

 

 

Duncanville Lateral (segment 90)

 

 

36

 

 

 

 

 

36

 

 

Dearmanville (segment 150)

 

 

355

 

 

 

 

 

355

 

 

White Castle (segment 340)

 

 

798

 

 

 

 

 

798

 

 

LA West Leg (segment 350)

 

 

798

 

 

 

 

733

(65)

Franklinton Compressor Station: Scheduled Unit Maintenance, Proj-512216 (3/18/2025 - 3/31/2025)

 

Sesh (segment 380)

 

 

506

 

 

 

 

 

506

 

 

 

Gwinville (segment 400)

 

 

234

 

 

 

 

 

65

(169)

Gwinville Pickens Line north of Gwinville: Pipeline Maintenance(remediation), Proj-SNG-19050/20646 (3/17/2025 - 3/24/2025)

Gwinville Pickens Line north of Gwinville: Pipeline Maintenance(remediation), Proj-SNG- 19050/20646/21938 (3/25/2025 - 4/4/2025)

Pickens Compressor Station: Scheduled Station Maintenance , Proj-4125 (3/25/2025 - 3/26/2025)

 

Enterprise (segment 430)

 

 

2,450

 

 

 

 

2200

(250)

Enterprise Compressor Station: Scheduled Unit Maintenance, Proj-522216 (3/24/2025 - 3/31/2025)

 

Ellerslie (segment 490)

 

 

1,663

 

 

 

 

 

1,663

 

 

South Atlanta (segment 510)

 

 

537

 

 

 

 

 

537

 

 

Thomaston East (segment 530)

 

 

900

 

 

 

 

 

900

 

 

East/South Wrens (segment 560)

 

 

724

 

 

 

 

669

(55)

Wrens Compressor Station: Scheduled Unit Maintenance, Proj-52885 (3/18/2025 - 3/31/2025)

 

South Georgia (segment 650)

 

 

143

 

 

 

 

 

143

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

 

-Restrictions to Primary In-Path transportation services may be necessary.

 

SNG - Outage Impact Report

 

 

-Restrictions to In-Path transportation services may be necessary.

 

April 2025 (updated 03/13/25)

 

 

-Restrictions to Interruptible and Out of Path transportation services may be necessary.

-No anticipated impact to transportation services.

 

Station / Seg

 

Est Nominal Design Capacity (Thousand Dth)

Week 1 (3/31 - 4/6)

Week 2 (4/7 - 4/13)

Week 3 (4/14 - 4/20)

Week 4 (4/21 - 4/27)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

 

Onward (segment 30)

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

 

Louisville East (segment 50)

 

 

520

 

 

520

 

210

(310)

 

210

(310)

 

275

(245)

2nd North Main Line east of Pickens: Pipeline Maintenance(remediation), Proj-SNG-19047 (4/21/2025 - 5/2/2025)

2nd North Main Line east of Pickens: Pipeline Maintenance(remediation), Proj-SNG-19047 (M) (4/8/2025 - 4/18/2025)

 

Duncanville Lateral (segment 90)

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

 

Pell City Station (segment 140)

 

 

474

 

 

474

 

 

474

 

 

474

 

304

(170)

Talladega Branch loop to Sylacauga line: Scheduled Pipeline Maintenance, Proj-SNG-36904 (M) (4/22/2025 - 4/24/2025)

 

 

Dearmanville (segment 150)

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

 

White Castle (segment 340)

 

 

772

 

 

772

 

 

772

 

 

772

 

 

772

 

 

 

LA West Leg (segment 350)

 

 

695

 

630

(65)

 

 

695

 

 

695

 

 

695

Franklinton Compressor Station: Scheduled Unit Maintenance, Proj-512216 (3/18/2025 - 3/31/2025)

 

 

Sesh (segment 380)

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

 

Gwinville Pool (segment 390)

 

 

1,607

 

1217

(390)

 

1217

(390)

 

1342

(265)

 

1342

(265)

Gwinville Compressor Station: Scheduled Station Maintenance, Proj-5211P4B (4/5/2025 - 4/12/2025) Gwinville Compressor Station: Scheduled Station Maintenance, Proj-5211P4C (4/12/2025 - 4/21/2025)

 

 

Gwinville (segment 400)

 

 

234

 

 

199

(35)

 

 

150

(84)

 

 

150

(84)

 

 

149

(85)

2nd North Main Line east of Pickens: Pipeline Maintenance(remediation), Proj-SNG-19047 (4/8/2025 - 4/18/2025)

Gwinville Pickens Line north of Gwinville: Pipeline Maintenance(remediation), Proj-SNG- 19050/20646/21938 (3/25/2025 - 4/4/2025)

Pickens Compressor Station: Scheduled Unit Maintenance , Proj-41251 (4/21/2025 - 5/11/2025)

 

 

Bay Springs (segment 420)

 

 

1,675

 

 

1,675

 

1485

(190)

 

 

1,675

 

 

1,675

Bay Springs Compressor Station: Scheduled Unit Maintenance, Proj-52163 (4/7/2025 - 4/10/2025)

 

 

Enterprise (segment 430)

 

 

2,306

 

2056

(250)

 

2136

(170)

 

 

2,306

 

 

2,306

Enterprise Compressor Station: Scheduled Unit Maintenance, Proj-522216 (3/24/2025 - 3/31/2025) Enterprise Compressor Station: Scheduled Unit Maintenance, Proj-522216 (4/1/2025 - 4/7/2025)

 

 

York (segment 440)

 

 

2,305

 

2125

(180)

 

2080

(225)

 

2125

(180)

 

2125

(180)

York Compressor Station: Scheduled Unit Maintenance, Proj-52301 (4/1/2025 - 10/31/2025) York Compressor Station: Scheduled Unit Maintenance, Proj-52303 (4/7/2025 - 4/9/2025)

 

 

Gallion (Segment 440)

 

 

2,300

 

2030

(270)

 

 

2,300

 

 

2,300

 

 

2,300

Gallion Compressor Station: Scheduled Unit Maintenance , Proj-523610 (3/31/2025 - 4/2/2025)

 

 

Selma (segment 460)

 

 

2,293

 

2043

(250)

 

 

2,293

 

 

2,293

 

 

2,293

Selma Compressor Station: Scheduled Unit Maintenance, Proj-52453 (4/2/2025 - 4/4/2025)

 

 

Auburn (segment 460)

 

 

1,953

 

 

1,953

 

 

1628

(325)

 

 

1628

(325)

 

 

1628

(325)

Auburn Compressor Station: Scheduled Unit Maintenance, Proj-52593 (4/23/2025 - 4/25/2025) South Main Loop Line east of Auburn: Scheduled Pipeline Maintenance, Proj-SNG-24941 (4/9/2025 - 4/23/2025)

South Main Loop Line west of Ellerslie: Scheduled Pipeline Maintenance, Proj-SNG-24942 (4/9/2025 - 4/23/2025)

 

 

Ellerslie (segment 490)

 

 

1,547

 

 

1,547

 

 

1,547

 

1317

(230)

 

 

1,547

Thomaston Compressor Station: Scheduled Unit Maintenance, Proj-52721 (4/14/2025 - 4/18/2025)

 

 

South Atlanta (segment 510)

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

 

Thomaston East (segment 530)

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

 

Hall Gate (segment 560)

 

 

705

 

635

(70)

 

635

(70)

 

635

(70)

 

635

(70)

Hall Gate Compressor Station: Scheduled Unit Maintenance, Proj-52833 (4/1/2025 - 5/11/2025)

 

East/South Wrens (segment 560)

 

 

680

 

625

(55)

 

 

680

 

 

680

 

 

680

Wrens Compressor Station: Scheduled Unit Maintenance, Proj-52885 (3/18/2025 - 3/31/2025)

 

 

South Georgia (segment 650)

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

 

 

Holy Trinity (segment 655)

 

 

127

 

 

127

 

97

(30)

 

97

(30)

 

 

127

Holy Trinity Compressor Station: Scheduled Station Maintenance (4/7/2025 - 4/12/2025) Holy Trinity Compressor Station: Scheduled Unit Maintenance, Proj-58051 (4/7/2025 - 4/12/2025)

Mainline #1 north of Holy Trinity Compressor Station: Scheduled Pipeline Maintenance (4/14/2025 - 4/20/2025)

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses. Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

 

 

-Restrictions to Primary In-Path transportation services may be necessary.

 

 

SNG - Outage Impact Report

 

 

-Restrictions to In-Path transportation services may be necessary.

 

 

May 2025 (updated 03/13/25)

 

 

-Restrictions to Interruptible and Out of Path transportation services may be necessary.

 

 

 

 

 

-No anticipated impact to transportation services.

 

Station / Seg

 

Est Nominal Design Capacity (Thousand Dth)

Week 1 (4/28 - 5/4)

Week 2 (5/5 - 5/11)

Week 3 (5/12 - 5/18)

Week 4 (5/19 - 5/25)

Week 5 (5/26 - 6/1)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Onward (segment 30)

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

Louisville East (segment 50)

 

 

520

 

275

(245)

 

 

520

 

 

520

 

 

520

 

 

520

2nd North Main Line east of Pickens: Pipeline Maintenance(remediation), Proj-SNG-19047 (4/21/2025 - 5/2/2025)

 

Duncanville Lateral (segment 90)

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

Dearmanville (segment 150)

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

White Castle (segment 340)

 

 

772

 

 

772

 

 

772

 

 

772

 

 

772

 

 

772

 

 

LA West Leg (segment 350)

 

 

695

 

 

695

 

 

695

 

 

695

 

535

(160)

 

535

(160)

Duck Lake Franklinton Line north of White Castle: Scheduled Pipeline Maintenance, Proj-SNG-22856 (5/22/2025 - 6/5/2025)

Duck Lake Franklinton Line north of White Castle: Scheduled Pipeline Maintenance, Proj-SNG-2753 (5/22/2025 - 6/5/2025)

 

Sesh (segment 380)

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

Gwinville Pool (segment 390)

 

 

1,607

 

1217

(390)

 

1217

(390)

 

 

1,607

 

 

1,607

 

 

1,607

Gwinville Compressor Station: Scheduled Station Maintenance, Proj-521113P5A (4/29/2025 - 5/2/2025)

Gwinville Compressor Station: Scheduled Station Maintenance, Proj-5211P5 (4/28/2025 - 5/8/2025)

 

 

Gwinville (segment 400)

 

 

234

 

 

0

(234)

 

 

149

(85)

 

 

150

(84)

 

 

150

(84)

 

 

234

2nd North Main Line east of Pickens: Pipeline Maintenance(remediation), Proj-SNG-19047 (5/5/2025 - 5/21/2025)

Pickens Compressor Station: Scheduled Unit Maintenance , Proj-41251 (4/21/2025 - 5/11/2025) 5/2/2025)

Gwinville Compressor Station: Scheduled Station Maintenance, Proj-5211P5 (4/28/2025 - 5/8/2025)

 

Enterprise (segment 430)

 

 

2,306

 

 

2,306

 

 

2,306

 

 

2,306

 

 

2,306

 

 

2,306

 

 

York (segment 440)

 

 

2,305

 

2125

(180)

 

2125

(180)

 

2125

(180)

 

2125

(180)

 

2125

(180)

York Compressor Station: Scheduled Unit Maintenance, Proj-52301 (4/1/2025 - 10/31/2025)

 

Selma (segment 460)

 

 

2,293

 

 

2,293

 

 

2,293

 

1993

(300)

 

 

2,293

 

 

2,293

South Main Loop Line east of Selma: Scheduled Pipeline Maintenance, Proj-SNG-24945 (5/12/2025 - 5/18/2025)

 

Auburn (segment 460)

 

 

1,953

 

1813

(140)

 

1813

(140)

 

 

1,953

 

 

1,953

 

 

1,953

South Main Loop Line west of Ellerslie: Scheduled Pipeline Maintenance, Proj-SNG-24943 (4/28/2025 - 5/11/2025)

South Main Loop Line west of Ellerslie: Scheduled Pipeline Maintenance, Proj-SNG-24944 (4/28/2025 - 5/11/2025)

 

Ellerslie (segment 490)

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

South Atlanta (segment 510)

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

Thomaston East

(segment 530)

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

Hall Gate (segment 560)

 

 

705

 

635

(70)

 

635

(70)

 

 

705

 

 

705

 

 

705

Hall Gate Compressor Station: Scheduled Unit Maintenance, Proj-52833 (4/1/2025 - 5/11/2025)

 

South Georgia (segment 650)

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses. Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

 

 

 

-Restrictions to Primary In-Path transportation services may be necessary.

 

 

SNG - Outage Impact Report

 

 

-Restrictions to In-Path transportation services may be necessary.

 

June 2025 (updated 03/13/25)

 

-Restrictions to Interruptible and Out of Path transportation services may be necessary.

-No anticipated impact to transportation services.

 

Station / Seg

 

Est Nominal Design Capacity (Thousand Dth)

Week 1 (6/2 - 6/8)

Week 2 (6/9 - 6/15)

Week 3 (6/16 - 6/22)

Week 4 (6/23 - 6/29)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Onward (segment 30)

 

 

203

 

 

203

 

 

203

 

 

203

 

 

203

 

 

Duncanville Lateral (segment 90)

 

 

36

 

 

36

 

 

36

 

 

36

 

 

36

 

 

Dearmanville (segment 150)

 

 

346

 

 

346

 

 

346

 

 

346

 

 

346

 

 

White Castle (segment 340)

 

 

772

 

 

772

 

 

772

 

 

772

 

 

772

 

 

 

LA West Leg (segment 350)

 

 

695

 

 

535

(160)

 

 

595

(100)

 

 

595

(100)

 

 

695

Duck Lake Franklinton Line north of White Castle: Scheduled Pipeline Maintenance, Proj-SNG-22856 (5/22/2025 - 6/5/2025)

Duck Lake Franklinton Line north of White Castle: Scheduled Pipeline Maintenance, Proj-SNG-2753 (5/22/2025 - 6/5/2025)

White Castle Franklinton Loop Line north of White Castle: Scheduled Pipeline Maintenance Proj-SNG-22856 (6/06/2025 - 6/17/2025)

 

Sesh (segment 380)

 

 

500

 

 

500

 

 

500

 

 

500

 

 

500

 

 

Gwinville (segment 400)

 

 

234

 

 

234

 

 

234

 

 

234

 

 

234

 

 

Enterprise (segment 430)

 

 

2,306

 

 

2,306

 

 

2,306

 

 

2,306

 

 

2,306

 

 

York (segment 440)

 

 

2,305

 

2125

(180)

 

2125

(180)

 

2125

(180)

 

2125

(180)

York Compressor Station: Scheduled Unit Maintenance, Proj-52301 (4/1/2025 - 10/31/2025)

 

Ellerslie (segment 490)

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

1,547

 

 

South Atlanta (segment 510)

 

 

522

 

 

522

 

 

522

 

 

522

 

 

522

 

 

Thomaston East (segment 530)

 

 

849

 

 

849

 

 

849

 

 

849

 

 

849

 

 

South Georgia (segment 650)

 

 

127

 

 

127

 

 

127

 

 

127

 

 

127

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.

The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.