Transco Notice 14448423
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Critical: | Y |
Notice Eff Date: | 04/05/2024 |
Notice Eff Time: | 15:26:46 CDT |
Notice End Date: | |
Notice End Time: | |
Notice ID: | 14448423 |
Notice Stat Desc: | Supersede |
Notice Type Desc: | Maint |
Post Date: | 04/05/2024 |
Post Time: | 15:26:46 CDT |
Prior Notice: | 14447674 |
Reqrd Rsp Desc: | No response required |
Rsp Date: | |
Rsp Time: | |
TSP: | 007933021 |
TSP Name: | TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC |
Notice Text:
Subject: 2024 Major Construction and Maintenance Projects
Please be advised that Transco’s major construction and maintenance schedule for projects that are currently planned for 2024 has been updated and can be accessed using the link below. The link to the maintenance schedule will also be available on the informational postings portion of the 1Line portal under the operational information tab.
While significant effort has been made to provide dates for the 2024 schedule, the dates and duration of the planned work are subject to change. Transco will provide revisions to the maintenance schedule as updated information is available.
Some of this work will affect the availability of interruptible transportation services (IT and secondary FT). The extent of this impact will depend on operating conditions at the time of the outage. If a maintenance activity is expected to affect the availability of transportation services, additional information will be posted prior to commencement of that activity.
Click here to access the 2024 Maintenance Schedule link.