Critical: | Y |
Notice Eff Date: | 11/20/2024 |
Notice Eff Time: | 08:37:47 CST |
Notice End Date: | |
Notice End Time: | |
Notice ID: | 15140898 |
Notice Stat Desc: | Initiate |
Notice Type Desc: | Maint |
Post Date: | 11/20/2024 |
Post Time: | 08:37:47 CST |
Prior Notice: | 0 |
Reqrd Rsp Desc: | Immediate response required of an operational nature may be required of impacted shippers |
Rsp Date: | |
Rsp Time: | |
TSP: | 007933021 |
TSP Name: | TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC |
Notice Text:
Subject: Station 80 Unplanned Compressor Unit Outage
Due to an unexpected equipment malfunction, Transco has experienced an unplanned outage on one of the compressor units at Station 80.
An exact return-to-service date for the impacted compressor is currently being determined, with repairs being expedited to ensure the quickest possible resolution. The current estimate is that repairs will not be completed until the week of December 2nd, and an additional posting will be published within the next week as more information is available about an exact return to service date. As a result of this compressor unit outage, the total quantity available through Station 80 includes all transportation priorities through the TSB .
During this period of unplanned maintenance, non-secondary reverse path (NSRP), secondary FT, and interruptible (IT) transactions moving south to north through the location will be available as operating capacity and conditions allow.
Operating Conditions resulting from this unplanned maintenance will require Transco to manage all transportation services moving south to north through the location listed below. The total quantity available will be contingent on system conditions during the unplanned maintenance period, but is anticipated to be limited to the quantity indicated below. Transactions moving north to south through this location will not be impacted.
The receipt-based Throughput Section Boundary (TSB) at mainline milepost 740.50 (Station 80) will be used to manage capacity availability including any required changes to the expected total quantity available during this planned work. An updated Market and Production Area constraint notice will include the location and the available quantity of transportation services during the indicated period.
TSB Name - Location |
Location ID |
Flow Direction |
Design Capacity (Mdt/d) |
Total Quantity Available (Mdt/d) |
% Cuts (Primary)Potential Shipper Impact (Based on Historical Utilization) |
Station 80 MP 740.50 |
9012483 |
South to North |
3,421 |
2,200 |
0-5% |