Type | Posted | Effective | End | Identifier | Status | Subject | Response |
---|---|---|---|---|---|---|---|
OFO | 09/05/25 | 09/04/25 | 09/18/25 | 3149 | VGT OFO Issued for Northern Natural Gas Company (NNG) delivery effective September 4, 2025, Timely Cycle | 09/04/25 | |
Oper Alert | 09/02/25 | 09/02/25 | 09/16/25 | 3147 | OFO Warning | ||
Plnd Outage | 08/14/25 | 08/12/25 | 08/16/25 | 3142 | COMPLETE: Viking Mainline - Planned Service Outage - HWY 65 MAOP | ||
Plnd Outage | 07/31/25 | 07/22/25 | 08/01/25 | 3141 | COMPLETE: Viking Mainline - Planned Service Outage - US Hwy 2 MAOP | ||
Constraint | 06/25/25 | 06/24/25 | 06/25/25 | 3131 | COMPLETE: Planned Capacity Constraint - Flow South of Chippewa Falls CS #2227 |