TSP Name: Viking Gas Transmission Company

TSP: 60-916-6673

Subject: Planned Service Outage - Flow South of Ada CS #2207

Notice Type: Constraint

Critical: Yes

Post Date/Time:: 03/07/2025 11:32 am

Notice Eff Date/Time: 04/15/2025 09:00 am

NOTICE_END_DATE: 04/15/2025 12:30 pm

Notice ID: 3097

Notice Stat Desc: Initiate

Prior Notice: 3097

Reqrd Rsp Desc: No response required

Rsp Date/Time:

Notice Text:

Due to planned maintenance at the Ada Compressor Station (CS) #2207, Viking Gas Transmission Company (VGT) will decrease the flow South of Ada CS #2207 capacity beginning Gas Day, Tuesday, April 15, 2025, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day, Tuesday, April 15, 2025, Intraday 1 (ID1) Cycle.

Flow South of Ada CS #2207 capacity will be reduced from 507,000 Dth to 425,000 Dth.

VGT does anticipate an impact to firm transportation service. Reservation charge credits will be applied pursuant to VGT's FERC Gas Tariff, General Terms and Conditions, Section 34.

Please contact your Commercial representative with questions.
TSP Name: Viking Gas Transmission Company

TSP: 60-916-6673

Subject: Planned Service Outage - Flow South of Ada CS #2207

Notice Type: Constraint

Critical: Yes

Post Date/Time:: 03/07/2025 11:32 am

Notice Eff Date/Time: 04/15/2025 09:00 am

NOTICE_END_DATE: 04/15/2025 12:30 pm

Notice ID: 3097

Notice Stat Desc: Initiate

Prior Notice: 3097

Reqrd Rsp Desc: No response required

Rsp Date/Time:

Notice Text:

Due to planned maintenance at the Ada Compressor Station (CS) #2207, Viking Gas Transmission Company (VGT) will decrease the flow South of Ada CS #2207 capacity beginning Gas Day, Tuesday, April 15, 2025, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day, Tuesday, April 15, 2025, Intraday 1 (ID1) Cycle.

Flow South of Ada CS #2207 capacity will be reduced from 507,000 Dth to 425,000 Dth.

VGT does anticipate an impact to firm transportation service. Reservation charge credits will be applied pursuant to VGT's FERC Gas Tariff, General Terms and Conditions, Section 34.

Please contact your Commercial representative with questions.