Westcoast Energy Notice 58188

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

 

Westcoast Energy Inc.

Critical Notice

Curtailment - Pipeline

 

Notice:

 #58188

Revision: 

 #0

 

Subject:

26" Alberta Mainline Capacity for April 29 - May 3, 2024

 

Summary:

26" Alberta Mainline Capacity for April 29 - May 3, 2024

As per notice #58042 & #58181 (Operationally Available Capacity for April & May 2024), Westcoast will be allowing the following flow on 26" Alberta Mainline:

26" Alberta West Capacity


April 29 - May 3, 2024:     0 GJ

Facilities on the Alberta Mainline East of CS1 will be allowed to flow to Gordondale (MS 134,165,185,198,162,161, and 199).


No Eastbound flows to Gordondale from Fort Nelson Mainline and Fort St. John Mainline (Includes MS 204 Taylor T-North). 

A full isolation is required for MS 84 Flatrock Creek for the duration of the outage.  


Dry Gas Over Production Charges will be in effect on the 26" Alberta Mainline during this outage. 
 


If you have any questions, please contact the CSR hotline at (403) 699-1800.

 

Posting Date:26-Apr-2024 08:29 CCT
Effective Date:29-Apr-2024
End Date:03-May-2024
Response Date:N/A
Location:N/A
Contacts:N/A
 

Westcoast Energy Inc.

Critical Notice

Curtailment - Pipeline

 

Notice:

 #58188

Revision: 

 #0

 

Subject:

26" Alberta Mainline Capacity for April 29 - May 3, 2024

 

Summary:

26" Alberta Mainline Capacity for April 29 - May 3, 2024

As per notice #58042 & #58181 (Operationally Available Capacity for April & May 2024), Westcoast will be allowing the following flow on 26" Alberta Mainline:

26" Alberta West Capacity


April 29 - May 3, 2024:     0 GJ

Facilities on the Alberta Mainline East of CS1 will be allowed to flow to Gordondale (MS 134,165,185,198,162,161, and 199).


No Eastbound flows to Gordondale from Fort Nelson Mainline and Fort St. John Mainline (Includes MS 204 Taylor T-North). 

A full isolation is required for MS 84 Flatrock Creek for the duration of the outage.  


Dry Gas Over Production Charges will be in effect on the 26" Alberta Mainline during this outage. 
 


If you have any questions, please contact the CSR hotline at (403) 699-1800.

 

Posting Date:26-Apr-2024 08:29 CCT
Effective Date:29-Apr-2024
End Date:03-May-2024
Response Date:N/A
Location:N/A
Contacts:N/A