Westcoast Energy Notice 58275

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

 

Westcoast Energy Inc.

Critical Notice

Curtailment - Pipeline

 

Notice:

 #58275

Revision: 

 #0

 

Subject:

Re-establishment Sunset Creek Interconnect Capacity for May 15, 2024 ID1

 

Summary:

Re-establishment Sunset Creek Interconnect Capacity for May 15, 2024 ID1

Westcoast will be allowing the following flow at Sunset Creek Interconnect:

Sunset Creek Interconnect Capacity

May 15, 2024 ID1 until further notice:      1,410,547 GJ

Changes in operating conditions may result in the capacity being recalled on any gas cycle.

If you have any questions, please contact the CSR hotline at (403) 699-1800.

 

Posting Date:15-May-2024 08:50 CCT
Effective Date:15-May-2024
End Date:20-May-2024
Response Date:N/A
Location:N/A
Contacts:N/A
 

Westcoast Energy Inc.

Critical Notice

Curtailment - Pipeline

 

Notice:

 #58275

Revision: 

 #0

 

Subject:

Re-establishment Sunset Creek Interconnect Capacity for May 15, 2024 ID1

 

Summary:

Re-establishment Sunset Creek Interconnect Capacity for May 15, 2024 ID1

Westcoast will be allowing the following flow at Sunset Creek Interconnect:

Sunset Creek Interconnect Capacity

May 15, 2024 ID1 until further notice:      1,410,547 GJ

Changes in operating conditions may result in the capacity being recalled on any gas cycle.

If you have any questions, please contact the CSR hotline at (403) 699-1800.

 

Posting Date:15-May-2024 08:50 CCT
Effective Date:15-May-2024
End Date:20-May-2024
Response Date:N/A
Location:N/A
Contacts:N/A