Westcoast Energy Notice 58553

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

 

Westcoast Energy Inc.

Critical Notice

Pipeline Operational Status

 

Notice:

 #58553

Revision: 

 #0

 

Subject:

Pipeline Operational Status for August 1, 2024 16:00 CCT

 

Summary:

       

System Linepack at 15:20 CCT:

3,199

  MMCF

 

Change Since Start of Gas Day August 01, 2024:

-41

  MMCF

 

Target Linepack for Gas Day August 01, 2024:

3,100

  MMCF

 
 

System Status at Report Time:

High LinepackHigh Linepack

System-Wide OFO in Effect:

No

Pack Tolerances:

Suppliers:

Minimum 500 GJ - Maximum of 8%

Non-Suppliers:

Minimum 500 GJ - Maximum of 2% up to 5,000 GJ

Marketers:

Mandatory zero balance

Draft Tolerances:

Suppliers:

Minimum 500 GJ - Maximum of 8%

Non-Suppliers:

Minimum 500 GJ - Maximum of 2% up to 5,000 GJ

Marketers:

Mandatory zero balance

 

Physical Operations Notes:

Linepack is expected to increase to an unhealthy level today.

 
 

Operational Status Details:

 

Report for Gas Day

 

Forecast for Gas Day

 

August 01, 2024

 

August 02, 2024

No details available for this Operational Status.

 

Pipeline Status:

Mainline North

Mainline Central

Mainline South

 

Commercial Notes:

Packed shippers must ensure accounts are within tolerance.

 

Estimated Imbalances at the end of Gas Day July 31, 2024:

Total Shipper Imbalances(GJ)

149,147

Total OBA Imbalances(GJ)

-21,336

System Gas on Pipe(GJ)

-1,876

 

A negative imbalance is owed to the Pipeline.

 

The above information is a forecast based on variable factors and as a result can change once actual data is validated.

If you have any questions, please call the CSR hotline at (403) 699-1800

 

Posting Date:01-Aug-2024 15:49 CCT
Effective Date:01-Aug-2024
End Date:01-Aug-2024
Response Date:N/A
Location:N/A
Contacts:N/A
 

Westcoast Energy Inc.

Critical Notice

Pipeline Operational Status

 

Notice:

 #58553

Revision: 

 #0

 

Subject:

Pipeline Operational Status for August 1, 2024 16:00 CCT

 

Summary:

       

System Linepack at 15:20 CCT:

3,199

  MMCF

 

Change Since Start of Gas Day August 01, 2024:

-41

  MMCF

 

Target Linepack for Gas Day August 01, 2024:

3,100

  MMCF

 
 

System Status at Report Time:

High LinepackHigh Linepack

System-Wide OFO in Effect:

No

Pack Tolerances:

Suppliers:

Minimum 500 GJ - Maximum of 8%

Non-Suppliers:

Minimum 500 GJ - Maximum of 2% up to 5,000 GJ

Marketers:

Mandatory zero balance

Draft Tolerances:

Suppliers:

Minimum 500 GJ - Maximum of 8%

Non-Suppliers:

Minimum 500 GJ - Maximum of 2% up to 5,000 GJ

Marketers:

Mandatory zero balance

 

Physical Operations Notes:

Linepack is expected to increase to an unhealthy level today.

 
 

Operational Status Details:

 

Report for Gas Day

 

Forecast for Gas Day

 

August 01, 2024

 

August 02, 2024

No details available for this Operational Status.

 

Pipeline Status:

Mainline North

Mainline Central

Mainline South

 

Commercial Notes:

Packed shippers must ensure accounts are within tolerance.

 

Estimated Imbalances at the end of Gas Day July 31, 2024:

Total Shipper Imbalances(GJ)

149,147

Total OBA Imbalances(GJ)

-21,336

System Gas on Pipe(GJ)

-1,876

 

A negative imbalance is owed to the Pipeline.

 

The above information is a forecast based on variable factors and as a result can change once actual data is validated.

If you have any questions, please call the CSR hotline at (403) 699-1800

 

Posting Date:01-Aug-2024 15:49 CCT
Effective Date:01-Aug-2024
End Date:01-Aug-2024
Response Date:N/A
Location:N/A
Contacts:N/A