East Tennessee Natural Gas Critical Notices
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Type | Posted | Effective | End | Identifier | Status | Subject | Response |
---|---|---|---|---|---|---|---|
Capacity Constraint | 04/23/25 | 04/24/25 | 04/25/25 | 161707 | ETNG Pipeline Conditions for 4/24/2025 | ||
Capacity Constraint | 04/22/25 | 04/23/25 | 04/24/25 | 161673 | ETNG Pipeline Conditions for 4/23/2025 | ||
Capacity Constraint | 04/21/25 | 04/22/25 | 04/23/25 | 161638 | ETNG Pipeline Conditions for 4/22/2025 | ||
Capacity Constraint | 04/20/25 | 04/21/25 | 04/22/25 | 161592 | ETNG Pipeline Conditions for 4/21/2025 | ||
Capacity Constraint | 04/19/25 | 04/20/25 | 04/21/25 | 161558 | ETNG Pipeline Conditions for 4/20/2025 | ||
Capacity Constraint | 04/18/25 | 04/19/25 | 04/20/25 | 161538 | ETNG Pipeline Conditions for 4/19/2025 | ||
Capacity Constraint | 04/17/25 | 04/18/25 | 04/19/25 | 161494 | ETNG Pipeline Conditions for 4/18/2025 | ||
Capacity Constraint | 04/16/25 | 04/17/25 | 04/18/25 | 161393 | ETNG Pipeline Conditions for 4/17/2025 | ||
Capacity Constraint | 04/15/25 | 04/15/25 | 07/14/25 | 161382 | Glade Spring Station and Portions of LN 3300-1/3300-2 Outage - UPDATE | ||
Operational Flow Order | 04/15/25 | 04/17/25 | 07/14/25 | 161344 | ETNG Operational Flow Order -- EFF 4/17 | ||
Capacity Constraint | 04/15/25 | 04/16/25 | 04/17/25 | 161361 | ETNG Pipeline Conditions for 4/16/2025 | ||
Operational Flow Order | 04/15/25 | 04/16/25 | 07/14/25 | 161339 | ETNG Operational Flow Order -- LIFTED | ||
Operational Flow Order | 04/15/25 | 04/16/25 | 07/14/25 | 161338 | ETNG Hourly Customer Specific Operational Flow Order -- LIFTED | ||
Capacity Constraint | 04/14/25 | 04/15/25 | 04/16/25 | 161326 | ETNG Pipeline Conditions for 4/15/2025 | ||
Capacity Constraint | 04/13/25 | 04/14/25 | 04/15/25 | 161289 | ETNG Pipeline Conditions for 4/14/2025 | ||
Capacity Constraint | 04/12/25 | 04/13/25 | 04/14/25 | 161259 | ETNG Pipeline Conditions for 4/13/2025 | ||
Capacity Constraint | 04/11/25 | 04/12/25 | 04/13/25 | 161202 | ETNG Pipeline Conditions for 4/12/2025 | ||
Capacity Constraint | 04/11/25 | 04/11/25 | 07/10/25 | 161180 | Glade Spring Station and Portions of LN 3300-1/3300-2 Outage - UPDATE | ||
Capacity Constraint | 04/10/25 | 04/11/25 | 04/12/25 | 161165 | ETNG Pipeline Conditions for 4/11/2025 | ||
Capacity Constraint | 04/09/25 | 04/10/25 | 04/11/25 | 161096 | ETNG Pipeline Conditions for 4/10/2025 | ||
Capacity Constraint | 04/08/25 | 04/09/25 | 04/10/25 | 161063 | ETNG Pipeline Conditions for 4/9/2025 | ||
Capacity Constraint | 04/07/25 | 04/08/25 | 04/09/25 | 161015 | ETNG Pipeline Conditions for 4/8/2025 | ||
Capacity Constraint | 04/06/25 | 04/07/25 | 04/08/25 | 160977 | ETNG Pipeline Conditions for 4/7/2025 | ||
Capacity Constraint | 04/05/25 | 04/06/25 | 04/07/25 | 160919 | ETNG Pipeline Conditions for 4/6/2025 | ||
Capacity Constraint | 04/04/25 | 04/05/25 | 04/06/25 | 160898 | ETNG Pipeline Conditions for 4/5/2025 | ||
Operational Flow Order | 04/03/25 | 04/07/25 | 07/02/25 | 160864 | ETNG Operational Flow Order | ||
Operational Flow Order | 04/03/25 | 04/07/25 | 07/02/25 | 160863 | ETNG Hourly Customer Specific Operational Flow Order | ||
Capacity Constraint | 04/03/25 | 04/04/25 | 04/05/25 | 160861 | ETNG Pipeline Conditions for 4/4/2025 | ||
Operational Flow Order | 04/03/25 | 04/03/25 | 07/02/25 | 160846 | ETNG Operational Flow Order -- EFF 4/4 -- CANCELLED | ||
Operational Flow Order | 04/03/25 | 04/03/25 | 07/02/25 | 160845 | ETNG Hourly Customer Specific Operational Flow Order -- LIFTED | ||
Capacity Constraint | 04/03/25 | 04/03/25 | 04/08/25 | 160844 | Clark Range to Wartburg 3100 Line Valve Section 2 Isolation -- COMPLETE | ||
Customer Services Update | 04/03/25 | 04/25/25 | 04/28/25 | 160805 | LINK System Maintenance the weekend of April 25, 2025 | ||
Operational Flow Order | 04/03/25 | 04/04/25 | 07/02/25 | 160794 | ETNG Operational Flow Order -- EFF 4/4 | ||
Capacity Constraint | 04/02/25 | 04/02/25 | 04/03/25 | 160793 | ETNG Pipeline Conditions for 4/2/2025 -- INTRADAY UPDATE | ||
Capacity Constraint | 04/02/25 | 04/03/25 | 04/04/25 | 160792 | ETNG Pipeline Conditions for 4/3/2025 -- INTRADAY | ||
Capacity Constraint | 04/02/25 | 04/02/25 | 04/03/25 | 160791 | ETNG Pipeline Conditions for 4/2/2025 -- INTRADAY | ||
Capacity Constraint | 04/02/25 | 04/03/25 | 04/04/25 | 160761 | ETNG Pipeline Conditions for 4/3/2025 | ||
Operational Flow Order | 04/02/25 | 04/03/25 | 07/01/25 | 160754 | ETNG Hourly Customer Specific Operational Flow Order -- EFF 4/3 | ||
Operational Flow Order | 04/02/25 | 04/02/25 | 04/03/25 | 160749 | ETNG Customer Specific Operational Flow Order -- EFF 4/2 | ||
Capacity Constraint | 04/01/25 | 04/02/25 | 04/03/25 | 160721 | ETNG Pipeline Conditions for 4/2/2025 | ||
Capacity Constraint | 03/31/25 | 04/01/25 | 04/02/25 | 160704 | ETNG Pipeline Conditions for 4/1/2025 -- Update | ||
Capacity Constraint | 03/31/25 | 04/01/25 | 04/02/25 | 160679 | ETNG Pipeline Conditions for 4/1/2025 | ||
Capacity Constraint | 03/30/25 | 03/31/25 | 04/01/25 | 160639 | ETNG Pipeline Conditions for 3/31/2025 | ||
Capacity Constraint | 03/29/25 | 03/30/25 | 03/31/25 | 160615 | ETNG Pipeline Conditions for 3/30/2025 | ||
Capacity Constraint | 03/28/25 | 03/29/25 | 03/30/25 | 160574 | ETNG Pipeline Conditions for 3/29/2025 | ||
Operational Flow Order | 03/27/25 | 03/29/25 | 04/01/25 | 160510 | ETNG Action Alert -- EFF 3/29 | ||
Capacity Constraint | 03/27/25 | 03/28/25 | 03/29/25 | 160535 | ETNG Pipeline Conditions for 3/28/2025 | ||
Capacity Constraint | 03/26/25 | 03/27/25 | 03/28/25 | 160472 | ETNG Pipeline Conditions for 3/27/2025 | ||
Capacity Constraint | 03/25/25 | 03/26/25 | 03/27/25 | 160433 | ETNG Pipeline Conditions for 3/26/2025 | ||
Capacity Constraint | 03/24/25 | 03/25/25 | 03/26/25 | 160392 | ETNG Pipeline Conditions for 3/25/2025 | ||
Capacity Constraint | 03/23/25 | 03/24/25 | 03/25/25 | 160352 | ETNG Pipeline Conditions for 3/24/2025 | ||
Capacity Constraint | 03/22/25 | 03/23/25 | 03/24/25 | 160321 | ETNG Pipeline Conditions for 3/23/2025 | ||
Capacity Constraint | 03/21/25 | 03/22/25 | 03/23/25 | 160311 | ETNG Pipeline Conditions for 3/22/2025 | ||
Operational Flow Order | 03/20/25 | 03/20/25 | 06/18/25 | 160227 | ETNG Action Alert -- EFF 3/22 | ||
Capacity Constraint | 03/20/25 | 03/21/25 | 03/22/25 | 160251 | ETNG Pipeline Conditions for 3/21/2025 | ||
Capacity Constraint | 03/19/25 | 03/20/25 | 03/21/25 | 160199 | ETNG Pipeline Conditions for 3/20/2025 | ||
Capacity Constraint | 03/18/25 | 03/19/25 | 03/20/25 | 160156 | ETNG Pipeline Conditions for 3/19/2025 | ||
Capacity Constraint | 03/17/25 | 03/18/25 | 03/19/25 | 160115 | ETNG Pipeline Conditions for 3/18/2025 | ||
Operational Flow Order | 03/17/25 | 03/18/25 | 03/20/25 | 160109 | ETNG Operational Flow Order | ||
Capacity Constraint | 03/16/25 | 03/17/25 | 03/18/25 | 160106 | ETNG Pipeline Conditions for 3/17/2025 | ||
Capacity Constraint | 03/15/25 | 03/16/25 | 03/17/25 | 160074 | ETNG Pipeline Conditions for 3/16/2025 | ||
Capacity Constraint | 03/14/25 | 03/15/25 | 03/16/25 | 160020 | ETNG Pipeline Conditions for 3/15/2025 | ||
Capacity Constraint | 03/13/25 | 03/14/25 | 03/15/25 | 159969 | ETNG Pipeline Conditions for 3/14/2025 | ||
Capacity Constraint | 03/12/25 | 03/13/25 | 03/14/25 | 159933 | ETNG Pipeline Conditions for 3/13/2025 | ||
Capacity Constraint | 03/11/25 | 03/12/25 | 03/13/25 | 159836 | ETNG Pipeline Conditions for 3/12/2025 | ||
Capacity Constraint | 03/10/25 | 03/11/25 | 03/12/25 | 159782 | ETNG Pipeline Conditions for 3/11/2025 | ||
Capacity Constraint | 03/09/25 | 03/10/25 | 03/11/25 | 159764 | ETNG Pipeline Conditions for 3/10/2025 | ||
Capacity Constraint | 03/08/25 | 03/09/25 | 03/10/25 | 159720 | ETNG Pipeline Conditions for 3/9/2025 | ||
Capacity Constraint | 03/07/25 | 03/08/25 | 03/09/25 | 159683 | ETNG Pipeline Conditions for 3/8/2025 | ||
Capacity Constraint | 03/06/25 | 03/07/25 | 03/08/25 | 159647 | ETNG Pipeline Conditions for 3/7/2025 | ||
Capacity Constraint | 03/05/25 | 03/06/25 | 03/07/25 | 159602 | ETNG Pipeline Conditions for 3/6/2025 | ||
Capacity Constraint | 03/04/25 | 03/05/25 | 03/06/25 | 159564 | ETNG Pipeline Conditions for 3/5/2025 | ||
Capacity Constraint | 03/03/25 | 03/04/25 | 03/05/25 | 159529 | ETNG Pipeline Conditions for 3/4/2025 | ||
Capacity Constraint | 03/02/25 | 03/03/25 | 03/04/25 | 159498 | ETNG Pipeline Conditions for 3/3/2025 | ||
Capacity Constraint | 03/01/25 | 03/02/25 | 03/03/25 | 159467 | ETNG Pipeline Conditions for 3/2/2025 | ||
Capacity Constraint | 02/28/25 | 03/01/25 | 03/02/25 | 159433 | ETNG Pipeline Conditions for 3/1/2025 | ||
Operational Flow Order | 02/28/25 | 03/01/25 | 03/03/25 | 159405 | ETNG Operational Flow Order -- EFF 3/1 | ||
Capacity Constraint | 02/27/25 | 02/28/25 | 03/01/25 | 159376 | ETNG Pipeline Conditions for 2/28/2025 | ||
Capacity Constraint | 02/26/25 | 02/27/25 | 02/28/25 | 159327 | ETNG Pipeline Conditions for 2/27/2025 | ||
Capacity Constraint | 02/25/25 | 02/26/25 | 02/27/25 | 159290 | ETNG Pipeline Conditions for 2/26/2025 | ||
Capacity Constraint | 02/24/25 | 02/25/25 | 02/26/25 | 159254 | ETNG Pipeline Conditions for 2/25/2025 | ||
Operational Flow Order | 02/24/25 | 02/24/25 | 05/25/25 | 159244 | ETNG Operational Flow Order -- LIFTED 2/25 | ||
Operational Flow Order | 02/24/25 | 02/24/25 | 05/25/25 | 159243 | ETNG Hourly Operational Flow Order -- LIFTED 2/25 | ||
Capacity Constraint | 02/23/25 | 02/24/25 | 02/25/25 | 159234 | ETNG Pipeline Conditions for 2/24/2025 -- Correction | ||
Capacity Constraint | 02/23/25 | 02/24/25 | 02/25/25 | 159208 | ETNG Pipeline Conditions for 2/24/2025 | ||
Operational Flow Order | 02/23/25 | 02/24/25 | 05/24/25 | 159206 | ETNG Operational Flow Order -- UPDATE | ||
Capacity Constraint | 02/23/25 | 02/23/25 | 02/24/25 | 159205 | ETNG Pipeline Conditions for 2/23/2025 -- Correction | ||
Capacity Constraint | 02/22/25 | 02/23/25 | 02/24/25 | 159175 | ETNG Pipeline Conditions for 2/23/2025 | ||
Capacity Constraint | 02/21/25 | 02/22/25 | 02/23/25 | 159136 | ETNG Pipeline Conditions for 2/22/2025 | ||
Capacity Constraint | 02/20/25 | 02/21/25 | 02/22/25 | 159102 | ETNG Pipeline Conditions for 2/21/2025 | ||
Capacity Constraint | 02/19/25 | 02/20/25 | 02/21/25 | 159035 | ETNG Pipeline Conditions for 2/20/2025 | ||
Capacity Constraint | 02/18/25 | 02/19/25 | 02/20/25 | 158995 | ETNG Pipeline Conditions for 2/19/2025 | ||
Capacity Constraint | 02/17/25 | 02/18/25 | 02/19/25 | 158981 | ETNG Pipeline Conditions for 2/18/2025 - UPDATE | ||
Operational Flow Order | 02/17/25 | 02/19/25 | 05/18/25 | 158950 | ETNG Operational Flow Order -- UPDATE | ||
Capacity Constraint | 02/17/25 | 02/18/25 | 02/19/25 | 158952 | ETNG Pipeline Conditions for 2/18/2025 | ||
Capacity Constraint | 02/16/25 | 02/17/25 | 02/18/25 | 158893 | ETNG Pipeline Conditions for 2/17/2025 | ||
Capacity Constraint | 02/16/25 | 02/16/25 | 02/17/25 | 158867 | ETNG Pipeline Conditions for 2/16/2025 -- INTRADAY | ||
Capacity Constraint | 02/15/25 | 02/16/25 | 02/17/25 | 158863 | ETNG Pipeline Conditions for 2/16/2025 | ||
Capacity Constraint | 02/14/25 | 02/15/25 | 02/16/25 | 158804 | ETNG Pipeline Conditions for 2/15/2025 | ||
Operational Flow Order | 02/13/25 | 02/13/25 | 05/14/25 | 158752 | ETNG Hourly Operational Flow Order -- EFF 2/18 | ||
Operational Flow Order | 02/13/25 | 02/13/25 | 05/14/25 | 158749 | ETNG Operational Flow Order -- EFF 2/16 | ||
Capacity Constraint | 02/13/25 | 02/13/25 | 05/14/25 | 158748 | ETNG MAD Notice -- EFF 2/16 | ||
Capacity Constraint | 02/13/25 | 02/14/25 | 02/15/25 | 158767 | ETNG Pipeline Conditions for 2/14/2025 | ||
Capacity Constraint | 02/12/25 | 02/13/25 | 02/14/25 | 158710 | ETNG Pipeline Conditions for 2/13/2025 | ||
Operational Flow Order | 02/11/25 | 02/13/25 | 05/12/25 | 158684 | Operational Flow Order -- EFF 2/13 | ||
Capacity Constraint | 02/11/25 | 02/12/25 | 02/13/25 | 158682 | ETNG Pipeline Conditions for 2/12/2025 | ||
Capacity Constraint | 02/10/25 | 02/11/25 | 02/12/25 | 158631 | ETNG Pipeline Conditions for 2/11/2025 | ||
Capacity Constraint | 02/09/25 | 02/10/25 | 02/11/25 | 158618 | ETNG Pipeline Conditions for 2/10/2025 | ||
Capacity Constraint | 02/08/25 | 02/09/25 | 02/10/25 | 158567 | ETNG Pipeline Conditions for 2/9/2025 | ||
Capacity Constraint | 02/07/25 | 02/08/25 | 02/09/25 | 158538 | ETNG Pipeline Conditions for 2/8/2025 | ||
Capacity Constraint | 02/06/25 | 02/07/25 | 02/08/25 | 158496 | ETNG Pipeline Conditions for 2/7/2025 | ||
Capacity Constraint | 02/05/25 | 02/06/25 | 02/07/25 | 158456 | ETNG Pipeline Conditions for 2/6/2025 | ||
Capacity Constraint | 02/04/25 | 02/05/25 | 02/06/25 | 158423 | ETNG Pipeline Conditions for 2/5/2025 | ||
Capacity Constraint | 02/03/25 | 02/04/25 | 02/05/25 | 158384 | ETNG Pipeline Conditions for 2/4/2025 | ||
Capacity Constraint | 02/02/25 | 02/03/25 | 02/04/25 | 158347 | ETNG Pipeline Conditions for 2/3/2025 | ||
Capacity Constraint | 02/01/25 | 02/02/25 | 02/03/25 | 158336 | ETNG Pipeline Conditions for 2/2/2025 | ||
Capacity Constraint | 01/31/25 | 02/01/25 | 02/02/25 | 158286 | ETNG Pipeline Conditions for 2/1/2025 | ||
Capacity Constraint | 01/30/25 | 01/31/25 | 02/01/25 | 158241 | ETNG Pipeline Conditions for 1/31/2025 | ||
Capacity Constraint | 01/29/25 | 01/30/25 | 01/31/25 | 158200 | ETNG Pipeline Conditions for 1/30/2025 | ||
Capacity Constraint | 01/28/25 | 01/29/25 | 01/30/25 | 158159 | ETNG Pipeline Conditions for 1/29/2025 | ||
Capacity Constraint | 01/27/25 | 01/28/25 | 01/29/25 | 158136 | ETNG Pipeline Conditions for 1/28/2025 -- UPDATE | ||
Capacity Constraint | 01/27/25 | 01/28/25 | 01/29/25 | 158128 | ETNG Pipeline Conditions for 1/28/2025 | ||
Other | 01/27/25 | 01/28/25 | 04/27/25 | 158116 | ETNG Imbalance Notice -- UPDATE | ||
Operational Flow Order | 01/27/25 | 01/27/25 | 04/27/25 | 158111 | ETNG Operational Flow Order -- LIFTED EFF 1/28 | ||
Capacity Constraint | 01/26/25 | 01/27/25 | 01/28/25 | 158084 | ETNG Pipeline Conditions for 1/27/2025 | ||
Capacity Constraint | 01/25/25 | 01/26/25 | 01/27/25 | 158054 | ETNG Pipeline Conditions for 1/26/2025 | ||
Capacity Constraint | 01/24/25 | 01/25/25 | 01/26/25 | 158025 | ETNG Pipeline Conditions for 1/25/2025 | ||
Capacity Constraint | 01/24/25 | 01/25/25 | 04/24/25 | 158006 | ETNG MAD Notice -- LIFTED EFF 1/25 |