ANR Pipeline Company Notice 12013

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP
006958581

TSP Name
ANR Pipeline Company

Notice Type Desc
Plnd Outage

Posting Date/Time
09/20/2024 5:35 pm

Notice Effective Date/Time
09/30/2024 9:00 am

Notice End Date/Time
10/08/2024 8:59 am

Notice ID
12013

Notice Status Desc
Supersede

Prior Notice
11995

Reqrd Rsp
5

Rsp Date/Time


Subject
UPDATED: CAPACITY REDUCTION Southwest Mainline Northbound (Updated: 9/20/24)

Notice Text
UPDATED: CAPACITY REDUCTION Southwest Mainline Northbound (Updated: 9/20/24)

Since the last posting, ANR has adjusted the capacity impact for the pipeline maintenance on the Southwest Mainline. ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. As a result, capacity will be reduced as follows:

9/30 - 10/1 Southwest Mainline Northbound (LOC #226630): 181 MMcf/d (leaving 525 MMcf/d)

Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
21% - Based on the Current Contracted MDQ

10/2 - 10/7 Southwest Mainline Northbound (LOC #226630): 146 MMcf/d (leaving 560 MMcf/d)

Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
16% - Based on the Current Contracted MDQ

Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule and deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract.

Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267


TSP
006958581

TSP Name
ANR Pipeline Company

Notice Type Desc
Plnd Outage

Posting Date/Time
09/20/2024 5:35 pm

Notice Effective Date/Time
09/30/2024 9:00 am

Notice End Date/Time
10/08/2024 8:59 am

Notice ID
12013

Notice Status Desc
Supersede

Prior Notice
11995

Reqrd Rsp
5

Rsp Date/Time


Subject
UPDATED: CAPACITY REDUCTION Southwest Mainline Northbound (Updated: 9/20/24)

Notice Text
UPDATED: CAPACITY REDUCTION Southwest Mainline Northbound (Updated: 9/20/24)

Since the last posting, ANR has adjusted the capacity impact for the pipeline maintenance on the Southwest Mainline. ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. As a result, capacity will be reduced as follows:

9/30 - 10/1 Southwest Mainline Northbound (LOC #226630): 181 MMcf/d (leaving 525 MMcf/d)

Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
21% - Based on the Current Contracted MDQ

10/2 - 10/7 Southwest Mainline Northbound (LOC #226630): 146 MMcf/d (leaving 560 MMcf/d)

Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
16% - Based on the Current Contracted MDQ

Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule and deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract.

Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267