ANR Pipeline Company Notice 12015

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP
006958581

TSP Name
ANR Pipeline Company

Notice Type Desc
Plnd Outage

Posting Date/Time
09/23/2024 2:20 pm

Notice Effective Date/Time
10/14/2024 9:00 am

Notice End Date/Time
10/20/2024 8:59 am

Notice ID
12015

Notice Status Desc
Initiate

Prior Notice
 

Reqrd Rsp
5

Rsp Date/Time


Subject
CAPACITY REDUCTION - Southeast Mainline - Cottage Grove Southbound (Posted: 9/23/24)

Notice Text
CAPACITY REDUCTION - Southeast Mainline - Cottage Grove Southbound (Posted: 9/23/24)

ANR has planned pipeline maintenance on the Southeast Mainline. As a result, capacity will be reduced as follows:

10/14 - 10/19 Cottage Grove Southbound (LOC #505614): 230 MMcf/d (leaving 1,003 MMcf/d)

ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. Estimated impact to Firm Primary as follows:
13% - Based on the Current Net Shipper Nominations
15% - Based on the Current Contracted MDQ

Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule and deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract. By means of this notice, ANR is establishing which specific Gas Days will be included when determining a shipper's 7-day Non-Force Majeure Average Usage Quantity pursuant to Section 6.36.2(b) of the Tariff.

Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267


TSP
006958581

TSP Name
ANR Pipeline Company

Notice Type Desc
Plnd Outage

Posting Date/Time
09/23/2024 2:20 pm

Notice Effective Date/Time
10/14/2024 9:00 am

Notice End Date/Time
10/20/2024 8:59 am

Notice ID
12015

Notice Status Desc
Initiate

Prior Notice
 

Reqrd Rsp
5

Rsp Date/Time


Subject
CAPACITY REDUCTION - Southeast Mainline - Cottage Grove Southbound (Posted: 9/23/24)

Notice Text
CAPACITY REDUCTION - Southeast Mainline - Cottage Grove Southbound (Posted: 9/23/24)

ANR has planned pipeline maintenance on the Southeast Mainline. As a result, capacity will be reduced as follows:

10/14 - 10/19 Cottage Grove Southbound (LOC #505614): 230 MMcf/d (leaving 1,003 MMcf/d)

ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. Estimated impact to Firm Primary as follows:
13% - Based on the Current Net Shipper Nominations
15% - Based on the Current Contracted MDQ

Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule and deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract. By means of this notice, ANR is establishing which specific Gas Days will be included when determining a shipper's 7-day Non-Force Majeure Average Usage Quantity pursuant to Section 6.36.2(b) of the Tariff.

Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267