ANR Pipeline Company Notice 12042

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP
006958581

TSP Name
ANR Pipeline Company

Notice Type Desc
Plnd Outage

Posting Date/Time
10/08/2024 10:35 am

Notice Effective Date/Time
10/22/2024 9:00 am

Notice End Date/Time
10/24/2024 8:59 am

Notice ID
12042

Notice Status Desc
Supersede

Prior Notice
12020

Reqrd Rsp
5

Rsp Date/Time


Subject
UPDATED: CAPACITY REDUCTION - Southeast Mainline - Brownsville Southbound (Updated: 10/8/24)

Notice Text
UPDATED: CAPACITY REDUCTION - Southeast Mainline - Brownsville Southbound (Updated: 10/8/24)

ANR has revised the dates for the planned maintenance at the Brownsville Compressor Station on the Southeast Mainline. As a result, capacity will be reduced as follows:

10/22 - 10/23 (Previously 10/24) Brownsville Southbound (LOC #1260569): 239 MMcf/d (leaving 988 MMcf/d)

ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. Estimated impact to Firm Primary as follows:
5% - Based on the Current Net Shipper Nominations
17% - Based on the Current Contracted MDQ

Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule and deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract.

Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267


TSP
006958581

TSP Name
ANR Pipeline Company

Notice Type Desc
Plnd Outage

Posting Date/Time
10/08/2024 10:35 am

Notice Effective Date/Time
10/22/2024 9:00 am

Notice End Date/Time
10/24/2024 8:59 am

Notice ID
12042

Notice Status Desc
Supersede

Prior Notice
12020

Reqrd Rsp
5

Rsp Date/Time


Subject
UPDATED: CAPACITY REDUCTION - Southeast Mainline - Brownsville Southbound (Updated: 10/8/24)

Notice Text
UPDATED: CAPACITY REDUCTION - Southeast Mainline - Brownsville Southbound (Updated: 10/8/24)

ANR has revised the dates for the planned maintenance at the Brownsville Compressor Station on the Southeast Mainline. As a result, capacity will be reduced as follows:

10/22 - 10/23 (Previously 10/24) Brownsville Southbound (LOC #1260569): 239 MMcf/d (leaving 988 MMcf/d)

ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. Estimated impact to Firm Primary as follows:
5% - Based on the Current Net Shipper Nominations
17% - Based on the Current Contracted MDQ

Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule and deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract.

Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267